Bridge rehabilitation and intersection project nearing completion

McCracken Road Project 2022-2023

Progress continues at the 3rd and McCracken St. intersection with crews completing over 75 percent of the project. Crews will pour the bridge deck after the holiday and do some miscellaneous cleaning up throughout the project area.


The end bents have been painted and sealed, both spans of the bridge have been painted, intermediate bent repair has been completed including painting, installation of deck pans finished, lights installed, and bridge sections set back on their foundation. 


Expansion joints were set in place, and rebar has been tied and is ready for the bridge deck pour. The handrail has been installed on top of the wall at 3rd and Jackson. Excavation of McCracken is in process and prepped for asphalt.


Thank you for your patience and cooperation during this major rehabilitation project. 
pic1pic3pic4MCCRACKEN PROGRESS

Facebook Twitter Email

Other News in General

mccracken project logo

3rd St. Intersection to be closed

Posted on: August 30, 2023
republic trash route

Republic Services announces new routes

Posted on: August 21, 2023
Welcome to the City of Ozark

Welcome to the City of Ozark

Posted on: August 17, 2023
Scam Alert

Scam Alert

Posted on: July 18, 2023